Hello all!
For a resource driven project in which actual work is entered in
timephased fashion through resource assignments, the following
situation is experienced:
In the task usage view, the aggregate of all the actual work reported
in the timescale pane (right side) does not equal the actual work
(computed by MS Project) reported on the left pane.
The situation is the same in the resource usage view.
Any hints as to why that would be?
Thanks,
Pierre