View Full Version : Start/Finish dates adjust automatically when I enter WORK


jdee
I have Task A that starts on 4/3/06 and finishes on 4/28/06. There are three
resources assigned to it. Only 40 hours of work will take place during this
timeframe. When I enter in 40, the finish date jumps to 4/7/06. How do I keep
this from happening?

I am using Project 2003

J

JulieS
Hi jdee,

If you create the task and enter 20 days duration, the task will start on
4/3 and end on 4/28. (Assuming the project starts on 4/3 and there are no
non-working days in the calendar other than weekends).

Split your screen using the Window > Split command. In the task form at the
bottom, select fixed duration as the task type. Click OK in the task form.

Then select the resource name from the drop-down list in the task form
underneath the heading Resource Name. Enter in the work for each resource.
Click OK and Project will calculate the assignment units based upon formula
Work/Duration.

I hope this helps. Let us know how you get along.

Julie

"jdee" wrote:

> I have Task A that starts on 4/3/06 and finishes on 4/28/06. There are three
> resources assigned to it. Only 40 hours of work will take place during this
> timeframe. When I enter in 40, the finish date jumps to 4/7/06. How do I keep
> this from happening?
>
> I am using Project 2003
>
> J

jdee
It did not work. If I start a task on 4/3 and finish on 4/28, and enter in 20
days duration, then split the screen, enter in 2 resources and assign 4 hours
to each resources, it changes the FINISH for the task to 4/3.

Any other thoughts?
Thanks

Jenna

"JulieS" wrote:

> Hi jdee,
>
> If you create the task and enter 20 days duration, the task will start on
> 4/3 and end on 4/28. (Assuming the project starts on 4/3 and there are no
> non-working days in the calendar other than weekends).
>
> Split your screen using the Window > Split command. In the task form at the
> bottom, select fixed duration as the task type. Click OK in the task form.
>
> Then select the resource name from the drop-down list in the task form
> underneath the heading Resource Name. Enter in the work for each resource.
> Click OK and Project will calculate the assignment units based upon formula
> Work/Duration.
>
> I hope this helps. Let us know how you get along.
>
> Julie
>
> "jdee" wrote:
>
> > I have Task A that starts on 4/3/06 and finishes on 4/28/06. There are three
> > resources assigned to it. Only 40 hours of work will take place during this
> > timeframe. When I enter in 40, the finish date jumps to 4/7/06. How do I keep
> > this from happening?
> >
> > I am using Project 2003
> >
> > J

jdee
I figured it out. I had to change Task Type to FIXED DURATION

"jdee" wrote:

> It did not work. If I start a task on 4/3 and finish on 4/28, and enter in 20
> days duration, then split the screen, enter in 2 resources and assign 4 hours
> to each resources, it changes the FINISH for the task to 4/3.
>
> Any other thoughts?
> Thanks
>
> Jenna
>
> "JulieS" wrote:
>
> > Hi jdee,
> >
> > If you create the task and enter 20 days duration, the task will start on
> > 4/3 and end on 4/28. (Assuming the project starts on 4/3 and there are no
> > non-working days in the calendar other than weekends).
> >
> > Split your screen using the Window > Split command. In the task form at the
> > bottom, select fixed duration as the task type. Click OK in the task form.
> >
> > Then select the resource name from the drop-down list in the task form
> > underneath the heading Resource Name. Enter in the work for each resource.
> > Click OK and Project will calculate the assignment units based upon formula
> > Work/Duration.
> >
> > I hope this helps. Let us know how you get along.
> >
> > Julie
> >
> > "jdee" wrote:
> >
> > > I have Task A that starts on 4/3/06 and finishes on 4/28/06. There are three
> > > resources assigned to it. Only 40 hours of work will take place during this
> > > timeframe. When I enter in 40, the finish date jumps to 4/7/06. How do I keep
> > > this from happening?
> > >
> > > I am using Project 2003
> > >
> > > J

jdee
It did not work. If I start a task on 4/3 and finish on 4/28, and enter in 20
days duration, then split the screen, enter in 2 resources and assign 4 hours
to each resources, it changes the FINISH for the task to 4/3.

Any other thoughts?
Thanks

Jenna

"JulieS" wrote:

> Hi jdee,
>
> If you create the task and enter 20 days duration, the task will start on
> 4/3 and end on 4/28. (Assuming the project starts on 4/3 and there are no
> non-working days in the calendar other than weekends).
>
> Split your screen using the Window > Split command. In the task form at the
> bottom, select fixed duration as the task type. Click OK in the task form.
>
> Then select the resource name from the drop-down list in the task form
> underneath the heading Resource Name. Enter in the work for each resource.
> Click OK and Project will calculate the assignment units based upon formula
> Work/Duration.
>
> I hope this helps. Let us know how you get along.
>
> Julie
>
> "jdee" wrote:
>
> > I have Task A that starts on 4/3/06 and finishes on 4/28/06. There are three
> > resources assigned to it. Only 40 hours of work will take place during this
> > timeframe. When I enter in 40, the finish date jumps to 4/7/06. How do I keep
> > this from happening?
> >
> > I am using Project 2003
> >
> > J

jdee
I figured it out. I had to change Task Type to FIXED DURATION

"jdee" wrote:

> It did not work. If I start a task on 4/3 and finish on 4/28, and enter in 20
> days duration, then split the screen, enter in 2 resources and assign 4 hours
> to each resources, it changes the FINISH for the task to 4/3.
>
> Any other thoughts?
> Thanks
>
> Jenna
>
> "JulieS" wrote:
>
> > Hi jdee,
> >
> > If you create the task and enter 20 days duration, the task will start on
> > 4/3 and end on 4/28. (Assuming the project starts on 4/3 and there are no
> > non-working days in the calendar other than weekends).
> >
> > Split your screen using the Window > Split command. In the task form at the
> > bottom, select fixed duration as the task type. Click OK in the task form.
> >
> > Then select the resource name from the drop-down list in the task form
> > underneath the heading Resource Name. Enter in the work for each resource.
> > Click OK and Project will calculate the assignment units based upon formula
> > Work/Duration.
> >
> > I hope this helps. Let us know how you get along.
> >
> > Julie
> >
> > "jdee" wrote:
> >
> > > I have Task A that starts on 4/3/06 and finishes on 4/28/06. There are three
> > > resources assigned to it. Only 40 hours of work will take place during this
> > > timeframe. When I enter in 40, the finish date jumps to 4/7/06. How do I keep
> > > this from happening?
> > >
> > > I am using Project 2003
> > >
> > > J

JulieS
Hi Jenna,

Glad you got it to work. I probably should have written my instructions
about setting the task type to fixed duration in quotes to make it easier to
spot.

Julie
"jdee" wrote in message
news:9FC4B8D6-2910-44CA-8397-A6BA199CABF4@microsoft.com...
>I figured it out. I had to change Task Type to FIXED DURATION
>
> "jdee" wrote:
>
>> It did not work. If I start a task on 4/3 and finish on 4/28, and enter
>> in 20
>> days duration, then split the screen, enter in 2 resources and assign 4
>> hours
>> to each resources, it changes the FINISH for the task to 4/3.
>>
>> Any other thoughts?
>> Thanks
>>
>> Jenna
>>
>> "JulieS" wrote:
>>
>> > Hi jdee,
>> >
>> > If you create the task and enter 20 days duration, the task will start
>> > on
>> > 4/3 and end on 4/28. (Assuming the project starts on 4/3 and there are
>> > no
>> > non-working days in the calendar other than weekends).
>> >
>> > Split your screen using the Window > Split command. In the task form at
>> > the
>> > bottom, select fixed duration as the task type. Click OK in the task
>> > form.
>> >
>> > Then select the resource name from the drop-down list in the task form
>> > underneath the heading Resource Name. Enter in the work for each
>> > resource.
>> > Click OK and Project will calculate the assignment units based upon
>> > formula
>> > Work/Duration.
>> >
>> > I hope this helps. Let us know how you get along.
>> >
>> > Julie
>> >
>> > "jdee" wrote:
>> >
>> > > I have Task A that starts on 4/3/06 and finishes on 4/28/06. There
>> > > are three
>> > > resources assigned to it. Only 40 hours of work will take place
>> > > during this
>> > > timeframe. When I enter in 40, the finish date jumps to 4/7/06. How
>> > > do I keep
>> > > this from happening?
>> > >
>> > > I am using Project 2003
>> > >
>> > > J



Steve House [Project MVP]
While you can set the task type to fixed duration and force the issue, does
it really make sense to do it that way? Why let your resources do the work
in drip and drops like that, spreading out over so long a time. Instead,
once they start have them go at it full tilt and just git 'er done. You've
said the task requires 40 hours of work, to be done by three people. That
means each person does about 13 man-hours of work. At 100% effort, 13 hours
of work is a little over 1 and a half 8-hour workdays. If the task can
start as early as 03 April, Monday, they can have it done, over with, and
out of the way well before the end of the day Tuesday the 4th. Why dawdle?
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"jdee" wrote in message
news:70349315-E1D5-4520-A177-A7918584DAA5@microsoft.com...
>I have Task A that starts on 4/3/06 and finishes on 4/28/06. There are
>three
> resources assigned to it. Only 40 hours of work will take place during
> this
> timeframe. When I enter in 40, the finish date jumps to 4/7/06. How do I
> keep
> this from happening?
>
> I am using Project 2003
>
> J