View Full Version : "Resource usage" view display the fields wrong!!


MAT
03-21-2006, 08:30 AM
Hello..
I have this problem:
Let's say I have 2 Enterprise-Projects which use the same enterprise
reources. The first project is completet.
I open the second one and use the "resource usage" view. I see by all
resources that their actual work by the first project is 0 and remaining work
is X. But they should be reverse.
So the problem is: The view "resource usage" shows instead of the fields
"actual work" the field "remaining work" and converse.
Can anybody help me for the Solution?
Thanks...

JulieS
03-21-2006, 12:17 PM
Hi MAT,

I assume by your reference to "enterprise projects" and "enterprise
resources" that you are using Project Server.

I suggest you post your question (if you haven't already) to the server
newsgroup (microsoft.public.project.server). For additional information on
the Project newsgroups see FAQ # 24 "Project Newsgroups" at:

http://project.mvps.org/faqs.htm

Julie

"MAT" <MAT@discussions.microsoft.com> wrote in message
news:83A30490-F0AB-4561-BB6A-D475C9687E49@microsoft.com...
> Hello..
> I have this problem:
> Let's say I have 2 Enterprise-Projects which use the same enterprise
> reources. The first project is completet.
> I open the second one and use the "resource usage" view. I see by all
> resources that their actual work by the first project is 0 and remaining
> work
> is X. But they should be reverse.
> So the problem is: The view "resource usage" shows instead of the fields
> "actual work" the field "remaining work" and converse.
> Can anybody help me for the Solution?
> Thanks...